Audit says 11 bln euros at risk on A400M -sources
viernes, 11 de diciembre de 2009
http://www.reuters.com/article/idUSGEE5BA1BR20091211?type=marketsNews
SEVILLE, Spain, Dec 11 (Reuters) - An independent audit commissioned
by A400M buyer nations has identified almost 11 billion euros of total
cost overruns or still at risk in the delayed plane project, sources
familiar with the matter said.